DAILY WORK ACCOMPLISHED by Dan Beltrami on NWAAC Taylorcraft
|
|
Log for N43387/SN-7046 |
|
|
November 2007 |
|
11/11 |
Pick up Airplane Fuselage and assorted parts |
|
11/15 |
Mount Control Column – Do SB2007-002 Inspection |
|
11/16 |
Inventory & install some pulleys. |
|
11/17 |
Make cardboard pattern – fwd. Floorboard. |
|
11/18 |
Make cardboard pattern
– aft floorboard |
|
11/19 |
Made after floorboard
from plywood. |
|
11/22 |
Work on Floor Boards. |
|
11/25 |
Word on Floor Boards. |
|
|
|
|
|
December 2007 |
|
12/02/07 |
.Two coats varnish on floorboards |
|
12/03/07 |
Made holes in instrument panel, airspeed, tachometer, altimeter |
|
12/07/07 |
Painted last coat varnish on floorboards, cut-out for glove box in instrument panel. Did logbook entry on Wing Strut Attachment Service Bulletin 2007-002. |
|
12/09/07 |
Make glove box for instrument panel. |
|
12/10/07 |
Filled out A/C Registration and Bill of Sale. Jim Breuer signed for the Northwest Antique Airplane Club. |
|
12/11/07 |
Mailed A/C Registration and title forms to FAA. |
|
12/17/07 |
Cut out oil temp, oil pressure gauge holes in instrument panel. Made and installed glove box to instrument panel. Cut out hole for ignition switch. Installed control wheel shaft bushings. |
|
12/18/07 |
Final fitting of all instruments into the panel. Installed glove box latch. Primer painted instrument panel. Permanently installed control yoke. |
|
12/19/07 |
Made template for instrument panel placards. |
|
12/24/07 |
Painted primer coat on rudder pedals. Final color painting of instrument panel and rudder pedals. |
|
|
|
|
|
January 2008 |
|
01/01/08 |
Worked on wheels and brake problems. |
|
01/03/08 |
Worked on wheels and brake problems. |
|
01/04/08 |
Determined how to fix the stripped holes in the left brake assembly. |
|
01/07/08 |
Installed instrument panel in airplane. |
|
01/08/08 |
Install left side aileron sprocket to control wheel. Get steel for rudder pedal clamps. |
|
01/09/08 |
Manufactured outboard rudder pedal hold down pivot blocks. |
|
01/10/08 |
Installed Heli-coil inserts into stripped holes on left brake holes. Rudder pedal installation. |
|
01/11/08 |
Shim brake pedal pivot cross tube with 9/16” washers. Manufacture special forming tool to make rudder pedal hold-down brackets. |
|
01/14/08 |
Rudder pedal installation. |
|
01/17/08 |
Rudder pedal installation. |
|
01/18/08 |
Rudder pedal installation. |
|
01/20/08 |
Installed instrument panel placard. Cleaned, inspected, tested, and installed engine tachometer; oil pressure and temperature gauges. |
|
01/22/08 |
Manufactured bushings for aileron chain and aileron pullies. |
|
01/22/08 |
Manufactured bushings for aileron chain and aileron pullies. |
|
01/30/08 |
Aileron pulley control system. |
|
01/31/08 |
Went to PCC and manufactured a new aileron control pulley. Manufactured 3 aileron system links. (Cabin overhead links). |
|
|
|
|
|
February 2008 |
|
02/01/08 |
Pulley installation in cabin area |
|
02/04/08 |
Pulley installation in cabin area |
|
02/05/08 |
Completed pulley installation in cabin area. |
|
02/06/08 |
Started fitting control wheels to control yoke. Paint and install control wheels. Started making brake system pulley brackets. |
|
02/08/08 |
Manufactured pulley brackets for the brake system. |
|
02/11/08 |
Manufactured pulley brackets for the brake system. |
|
02/13/08 |
Tack-welded brake system pulley brackets. |
|
02/14/08 |
Finished welding brake system pulley brackets. |
|
02/19/08 |
Installed aileron cables behind the instrument panel. |
|
02/25/08 |
Completed aileron cable installation. Synchronized control wheels. |
|
02/28/08 |
Tack-welded center brake pulley brackets to the fuselage cross-tube. |
|
|
|
|
|
March 2008 |
|
03/04/08 |
Welded left side brake pulley bracket. |
|
03/05/08 |
Completed and mailed form 337 for fabric cover job. |
|
03/06/08 |
Installed altimeter. |
|
03/07/08 |
Welded right side brake pulley bracket in place. Burnt a big hole in the fabric! |
|
03/13/08 |
Went to FAA. Asked the question! May we use the form 337 that approved the C-85 installation as approved data to allow us to re-install the C-85 onto this airframe? (See Attachment “A”.) |
|
03/14/08 |
Final hook up of left brake cables. |
|
03/17/08 |
Final hook up of right brake cables. |
|
03/18/08 |
More work on right brake system. |
|
03/18/08 |
Install rudder pedal return spring. |
|
03/24/08 |
Made and installed right and left rudder cables. Ordered new airspeed indicator from Chief Aircraft. Installed rudder pedal cabe fairleads. |
|
03/25/08 |
Cleaned and installed fuel tank on/off valve. Leak tested with 3 gallons gas. |
|
03/26/08 |
Placarded airspeed indicator with VRC, caution range, and normal operating range arcs. Installed throttle. |
|
03/27/08 |
Installed airspeed indicator in instrument panel. |
|
03/28/08 |
Manufactured & installed fuel valve shut off clip in accordance with AD51-09-03. |
|
03/31/08 |
Test fit boot cowl to fuselage. Check doors for fit. |
|
|
|
|
|
April 2008 |
|
04/01/08 |
Permanently screwed forward door jams to fuselage. Removed fuel tank cross brace rods, cleaned, primed and and re-installed. |
|
04/03/08 |
Cleaned boot cowl, removed really ugly repair section on bottom of cowl, manufactured patch for the left side of boot cowl. |
|
04/04/08 |
Finish making left side boot cowl patch. |
|
|
|
From Dan Beltrami’s handwritten shop notes, typed by Vanessa Jump Nelson